IMACS facility instrument status

This is based on the [WWW]Magellan Facility Instruments Policy, Revision E, April 15, 2002, document number 01PM004, which takes precedence over this list.

Proposal

Secton 2.1 of the policy document. I suggest there doesn't need to be a proposal to the SAC to build IMACS. IMACS PDR was in 1999, well before the facility instrument policy was drafted (2001).

Magellan Facility Instrument SAC Proposal Checklist
ItemStatus
Scientifc applicationsNA
Instrument specificationsNA
Instrument requirementsNA
BudgetNA
ScheduleNA
Discussed with observatory staffNA
Link to written proposalNA

Supplemental report

Section 2.2. Observatory staff and instrument group work together to estimate the resources needed for installation and routine operations. Together, they produce a report that specifies the responsibilities of each for installing, maintaining, and servicing the instrument.

Again, these are not relevant for IMACS (although a final support agreement should be done; see below).

Magellan Facility Instrument Supplemental Report Checklist
ItemStatus
Estimate installation resources (2.2a)NA
Estimate support requirements (2.2b)NA
Agreements on installation, maintenance, and service (2.2c)NA
Link to written reportNA

Recommendations and approvals

These are not relevant for IMACS since it was conceived before the facility instrument policies.

ItemStatus
Submit proposal and supplemental report to SAC (2.2)NA
SAC recommendation to Council (link & date) (2.3)NA
Council approval (link & date) (2.4)NA

Liaison

Section 3.1. AU has asked the director to appoint a liaison (2/24/04). Michael Rauch (CIW) was appointed.

Monitoring

Section 3.2. [WWW]Occasional reports to the SAC.

Final support agreement

Section 3.3 and appendix. IMACSSupportAgreement This needs to be done and will be the most work.

Reviews and acceptance

Shipping and Commissioning
ItemStatus
Final support agreement acceptance by observatory staff (3.3)To-do
Director's pre-ship review (3.4)[WWW]PSR
Commissioning plan (with observatory staff; 3.5)To-do
Engineering time awardDone
Commissioning report presented to SACTo-do
SAC performance review (4.1a)To-do
Documents delivered (4.1b)In-progress
Spares delivered (4.1c)In-progress
Observatory staff training (4.1d)To-do
Support agreement (4.1e)To-do
Observatory staff notification to SAC on 4.1b-d (4.2)To-do
SAC recommendation to Council (4.2)To-do
Council acceptance (4.3)To-do


acl 2004-03-01 <au AT ociw DOT edu>