Engineering work schedule for July 2005

Baade July 20-22

Night time tests

  1. Collimation tests (active-passive) (Osip)
  2. Rotator Guiding & Non sidereal tracking tests (Skip)

Daytime work

  1. Remove Panic check guider stages (Martin)

Clay July 16-18

Night time tests

  1. LDSS encoder upgrade checkout (Osip?, Bagish, Birk)
  2. Comet follow up
  3. LDSS tests

Daytime work

  1. LDSS encoder upgrades (Bagish 7/13-7/18, Birk 7/14-7/19)
  2. MIKE Iodine Cell Acromag Module Installation (Jones/Leroy 7/16)

    MIKE Iodine cell guider automation (Birk 7/14-7/19)

  3. Modify quick look to allow flips in both directions (Birk)
  4. Magic camera service (Osip, Bravo)
  5. Rotator Master/Slave encoder Status Hardware implementation (Jones 7/16 7/18)