October 10-11 (daytime only)
1. MMTF installation into IMACS (Birk, Hare, Veilleux, Weiner, Rupke, Bland-Hawthorn). Install etalon in grating position, install controller in equipment rack on platform, test controls with calibration lamps.
October 12-14
Night time tests
1. Collimation tests (active-passive)
2. MMTF commissioning (Birk, Hare, Veilleux, Weiner, Rupke, Bland-Hawthorn, pending etalon delivery and testing in Pasadena). Expecting to use one full night for engineering tests.
3.
Daytime work
1. MMTF commissioning (see above) plus time after engineering for staff debriefing.
October 15-18
Night time tests
1.
2.
Daytime work
1. Remove M3 assembly, test fit f5 cell hardware from Harvard SAO
2. Test fit f5 instrument mounting ring and lift cart
3. Begin enclosure shutter alignment